Project Completion Hours Estimator
Estimate remaining effort using an entered completion rate.
How Project Completion Hours Estimator Works?
The Project Completion Hours Estimator works by dividing hours spent by the percentage complete to project total effort, then subtracting hours spent to estimate hours left.
- 1
Enter hours spent
Type hours used, for example 90 hours.
- 2
Enter percent complete
Type the completion rate, for example 40%.
- 3
Read the projection
Projected total = 90 ÷ 0.40 = 225 hours; estimated remaining = 135 hours.
Project Completion Hours Estimator Formula
The Project Completion Hours Estimator formula is Projected Total = Hours Spent ÷ Completion Rate, and Estimate to Complete = Projected Total − Hours Spent.
- Spent: hours used so far.
- %Complete: completion rate as a decimal (40% = 0.40).
- EAC: estimate at completion.
- ETC: estimate to complete.
Example: 140 hours spent at 56% complete project 250 total hours and 110 hours to complete. Against a 200-hour budget, the projected overrun is 50 hours.
Project Completion Hours Estimator Conversion Table
The Project Completion Hours Estimator conversion table shows projections for 120 hours spent at 6 completion rates.
| Hours Spent | % Complete | Projected Total | Hours to Complete |
|---|---|---|---|
| 120 | 20% | 600 | 480 |
| 120 | 30% | 400 | 280 |
| 120 | 40% | 300 | 180 |
| 120 | 50% | 240 | 120 |
| 120 | 60% | 200 | 80 |
| 120 | 80% | 150 | 30 |
What is Project Completion Hours Estimator?
The Project Completion Hours Estimator is a projection tool that forecasts total project effort from progress to date.
The original estimate stops being reliable once work starts. The Project Completion Hours Estimator uses the actual rate of progress, so a project 56% done after 140 hours projects 250 total hours.
What are the uses of Project Completion Hours Estimator?
There are 5 main uses of the Project Completion Hours Estimator, including overrun warnings, budget requests, and earned value reports.
-
Overrun warnings
Project managers see a 50-hour projected overrun early.
-
Budget requests
Teams request extra hours with a projection attached.
-
Earned value reports
Planners report estimate at completion (EAC).
-
Construction progress
Site managers project labor hours from percent complete.
-
Content production
Writers project total hours for a book 30% written.
Project Completion Hours Estimator FAQ
How do I use the Project Completion Hours Estimator?
1. Enter hours spent: Type hours used, for example 90 hours. 2. Enter percent complete: Type the completion rate, for example 40%. 3. Read the projection: Projected total = 90 ÷ 0.40 = 225 hours; estimated remaining = 135 hours.
What formula does the Project Completion Hours Estimator use?
The Project Completion Hours Estimator formula is Projected Total = Hours Spent ÷ Completion Rate, and Estimate to Complete = Projected Total − Hours Spent. In short: EAC = Spent ÷ %Complete; ETC = EAC − Spent.
Can you show a worked example?
140 hours spent at 56% complete project 250 total hours and 110 hours to complete. Against a 200-hour budget, the projected overrun is 50 hours.